"This is the third round of plans I have seen in the last 10 years, and this is the best." A member said that at the Community Center renovation Town Hall on April 23, 2025, and the June 2025 Pelican Bay Post printed it with other member comments. The room was full, and nearly 200 more members joined online. The timeline presented that day targeted spring 2027 for groundbreaking on the fitness addition.

Nineteen months later, the Foundation's FY2027 budget still lists the renovation as a project under consideration, and the plan has grown into something larger. The Foundation now treats the center as one piece of a campus-wide question that also takes in the restaurants and the beach tram. That explains why this season's biggest changes are at Marker 36 and Sandbar, while the Community Center's changes are limited to longer seasonal hours.

What the 2025 plan would have built

The committee recommended a design called Option 2. According to the July 2025 Post, it added an 18,000-square-foot fitness wing on the east side of the existing building, set on a parking podium so no spaces would be lost. The current building would be renovated for meetings, activities and lifestyle programs, with a café and activities lounge, a large outdoor patio overlooking the lake, a bigger art room and bocce courts.

At the April 2025 Town Hall, Community Master Plan Sub-Committee Chair Susan Levine estimated Option 2 at $40 million. That worked out to a suggested $1,000 to $2,000 per member, spread over two to three years. Foundation President Tony D'Errico opened the meeting by arguing for "continuous and disciplined reinvestment," and he pointed out that communities across Southwest Florida were spending heavily on lifestyle facilities.

Members asked for more than the plan included. Some wanted four to six bocce courts in place of two. Others wanted a lap pool, a fitness wing built so a fourth floor could be added later, and a Pilates room big enough for four to six reformers. A Pelican Bay Women's League representative said the league has 1,100 members in 32 interest groups. She asked for more activity and meeting space, room for cooking classes and a space with good acoustics for concerts.

On May 21, 2025, the Board approved up to $250,000 for WJ Architects to carry Option 2 into design development, paid from existing capital fund balances. The work was scheduled for June 1 to October 15, and the Post said finishing it over the summer would "keep the project on schedule for an April 2027 groundbreaking."

Parking became the hard question

By December 2025, Levine's update in the Pelican Bay Post called parking "the biggest hurdle we currently face." The subcommittee wanted to expand without a large parking garage, because a garage adds cost and creates problems such as fire department access. A professional parking study at the Community Center was planned for the end of January 2026. The same update said the subcommittee had studied three member requests: four bocce courts, a lap pool and a walking path around the lake. It also said the $40 million cost and how to pay for it were "top of mind for everyone."

A bigger building brings more members to the same lot at the same hours. Those same hours are when they head to lunch and wait for the tram. That overlap is the reason the next step looked at the whole campus.

The study that widened the question

By spring 2026, the Foundation was nearing the end of Phase One of its engagement with The Connors Group, a study of the member experience across Pelican Bay. The May/June 2026 Post said Phase One drew on more than 1,400 member survey responses, hundreds of member journey studies and detailed utilization reviews. According to the Foundation, the challenges members run into, "particularly within dining, the Community Center and tram service, are not isolated issues," but "inter-connected constraints related to capacity, process and design."

That same issue described where this leads: "a comprehensive, phased roadmap, prioritizing operational enhancements first, followed by targeted capital investments."

The July/August/September 2026 Post listed the priorities that came out of Phase One. They were restaurant access and capacity, the Community Center's space and equipment needs, and better visibility for members into tram arrivals and service disruptions. The next phase turns those findings into specific design and capacity requirements. After that, Phase Three is meant to give management and the Board "multiple implementation options and design scenarios that consider the needs of the entire Pelican Bay campus, including the Community Center," with stakeholder working sessions to narrow the choices.

The Foundation's FY2027 approved budget reflects the same order. Its capital fund cash projection lists the Community Center Renovation under "Projects under Consideration," with $217,000 spent in FY2025, $101,000 forecast for FY2026 and no amounts projected from FY2027 through FY2030. Pelican Bay Community Park is listed with the approved projects, at about $4.6 million in FY2025 and $1.4 million forecast for FY2026. The Community Center decision is still open.

This season, the first changes are at the restaurants

The "operational enhancements first" approach is easiest to see in dining. The October 2026 Post introduced a new food and beverage leadership team of five people across three restaurants. Marco Garnica is Director of Food and Beverage. Chef Fabio Bermudez, Director of Culinary – North, and Christopher Wright, Director of Operations – North, lead Marker 36. Chef Rushaune "Rush" Thompson, Director of Culinary – South, and Kevin Adames, Director of Operations – South, lead Sandbar and The Nest. In the same issue, Michael Broughton, Deputy General Manager of Community & Member Experience, said the team will "deliver improvements you can see, taste and feel."

General Manager John Wysseier opened the November 2026 Post by saying food and beverage operations are "entering a new chapter" with "a renewed emphasis on quality, consistency and service." He also mentioned a redesigned Today in the Bay newsletter and new digital tools for member services, and the same issue says Design Review now accepts applications through a new digital platform. Each of these changes costs far less than a building and can reach members within the same season.

At the Community Center, the November Post lists a new seasonal schedule. The desk is open weekdays from 9 a.m. to 7 p.m., subject to change, while the summer issue listed 8:30 a.m. to 5 p.m. Staffed fitness center hours are 6 a.m. to 7 p.m. on weekdays, 6 a.m. to 3 p.m. on Saturdays and 8 a.m. to 3 p.m. on Sundays. Members can also use the fitness center without staff early in the morning and in the evening.

Thanksgiving Day on the campus

According to the November Post, Thanksgiving Buffet is served at both Sandbar and Marker 36 on Thursday, November 26. First seating is at 11:30 a.m. and last seating is at 6:30 p.m. Trams run from 7 a.m. until the restaurants close. Community Park is open 8 a.m. to dusk, and the beach is open 9 a.m. to sunset.

The tram plan for the holiday matches a regular peak-season day. The FY2027 budget schedules 14 trams per shift and 28 per day for Thanksgiving Week, including two express units. That is the same deployment it lists for every period from November 1 through April 30. The FY2026 schedule shows the same numbers.

Coach Kim's "Fitness Before Feasting," her Thanksgiving fitness tradition, is back for an 11th year, and the November Post's fitness pages have the details. The same issue covered the Speaker Series opener, a Veterans Day presentation called "A Veteran's Story," and announced that the Pelican Bay Photography Show is returning with a new category for 2027.

What comes next for the building

The questions about the Community Center are broader now than they were at the April 2025 Town Hall. The study's later phases look at the building together with dining and tram capacity. The Connors Group's Phase Three is meant to give management and the Board several campus-wide scenarios, refined in working sessions with stakeholders. The July/August/September Post said the full Connors Group presentation can be found through a QR code printed in that issue. Foundation Board meetings are held at the Community Center and on Zoom, and the November Post directs members to pelicanbay.org for meeting updates. For a wider look at how Pelican Bay's shared amenities fit into daily life, see our Pelican Bay neighborhood page and our guide to Pelican Bay condo amenities.

Pelican Bay owners thinking about timing should know where the Community Center and the other shared amenities stand before deciding to hold, renovate or sell. The Norgart Team follows each phase of the Foundation's planning and can talk it through with you privately. Become a VIP and request private access.